PROJECT AUTHORIZATION PACKET ID: PMT-BKVC
CONTRACT ID EMARS PROGRAM CODE AUTHORIZATION NO:
8930702R      89307 5
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized.
PROJECT ID PROJECT ID NUMBER FEDERAL PROJECT NUMBER 6 YR PLAN ITEM NUMBER 6 YR PLAN ITEM PARENT NUMBER
093 007 1 020-021

0711120

05-00483 5-.-
PROJECT TYPE PROJECT LENGTH NUMBER OF BRIDGES SYSTEMS
MAJOR WIDENING
PROJECT PHASE
&
RESPONSIBILITY
PLANNING DESIGN RIGHT OF WAY UTILITIES
CONSTRUCTION TITLE DEEDED TO: MAINTENANCE OTHER
FUNDING & TIME
ACCOUNTABILITY
PARTICIPATING AGENCIES
FEDERAL FHWA STATE LOCAL OTHER
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER PHASE FUND PROGRAM FEDERAL FISCAL YEAR STATE FISCAL YEAR
FEDERAL APPR
CODE
CURRENT FUNDING REQUEST
5-483.3 R 1200 FD52 2019 2019 M001 $1,600,000.00
CURRENT FUNDING REQUEST TOTAL: $1,600,000.00
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES
PHASE TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST)
PLANNING $0.00
DESIGN $11,200,000.00
UTILITIES $565,000.00
R/W $2,000,000.00
CONSTRUCTION $0.00
NON-HIGHWAYS $0.00
  Total: $13,765,000.00
REMARKS: THIS AUTHORIZATION PROVIDES $1.6 M FEDERAL R/W FUNDS FOR THE PROJECT. LC
 
Project Approval Recommended By:
John Moore   7/7/2019
Signed and Approved by:
Andy Barber   7/8/2019
AUTHORIZATION LOCATION
ITEM NO. COUNTY DIST FACILITY NAME
ROUTE LENGTH SCOPE
05-00483.30 OLDHAM


5 BUCKNER - LAGRANGE I 71 CONSTRUCT NEW I-71 INTERCHANGE BETWEEN KY-393 AND KY-53 TO RELIEVE CONGESTION IN LAGRANGE.